OVERHAUL OF THE 400 KV MOLDAVSKA TPP – VULCĂNEȘTI OHL
- Client:
- CJSC “Moldavskaya GRES” (Inter RAO UES)
- Scope of work:
- Overhaul of the 400 kV Moldavska TPP – Vulcănești OHL
- Industry:
- Power engineering
- Location:
- Moldova
- Project timeline:
- 2010-2011
Project description
Commissioned by CJSC “Moldavskaya GRES” (Republic of Moldova), Soyuz Corporation overhauled the 400 kV Moldavska TPP – Vulcănești overhead line. The work was carried out in difficult conditions in the border zone between Ukraine and Moldova, in the wetlands of the Dniester estuary (Ukraine), where the line crosses the Dniester river. The schedule was agreed with the state enterprise Moldelectrica, and the work was carried out while the line was temporarily de-energised. The overhaul significantly improved the reliability of the power hub in the south of Odesa region (Ukraine) and the southern regions of the Republic of Moldova.