CONSTRUCTION OF THE 750 KV “RIVNE NPP – KYIVSKA SUBSTATION” OHL
- Client:
- SE NPC “Ukrenergo”
- Scope of work:
- Construction of the 750 kV Rivne NPP – Kyivska substation OHL
- Industry:
- Power engineering
- Location:
- Rivne region, Ukraine
- Project timeline:
- 2013-2015
Project description
NPC “Ukrenergo” put into operation the 750 kV Rivne NPP – Kyivska substation overhead line. The line increases the capacity available to the Kyiv power hub by 700 MW generated by Rivne Nuclear Power Plant, which in turn reduces the need for thermal generation. Construction took four years. The line is 353 km long, of which 109 km were built by Soyuz Corporation. The project was financed by SE NPC “Ukrenergo” and by loans from the European Bank for Reconstruction and Development and the European Investment Bank.