TECHNICAL RE-EQUIPMENT OF THE 330 KV “NOVOKYIVSKA” SUBSTATION
- Client:
- SE NPC “Ukrenergo”
- Scope of work:
- Technical re-equipment of the 330 kV Novokyivska substation: design, manufacture, supply, installation, testing, adjustment and commissioning under the works contract
- Industry:
- Power engineering
- Location:
- Kyiv region, Ukraine
- Project timeline:
- 2017-2021
Project description
In 2017 the association of Soyuz Corporation (Ukraine) and Soyuzkomplekt JV LLC (Kazakhstan) signed a contract with SE NPC “Ukrenergo” for the technical re-equipment of the 330 kV Novokyivska substation. The design was carried out by Soyuzenergoproekt LLC, Kharkiv, Ukraine. The project covered the design, manufacture, testing and supply of 330 kV and 110 kV gas-insulated switchgear, autotransformers AT-3 and AT-2 and other equipment, as well as installation, adjustment and commissioning. Construction, installation and commissioning were carried out by Ukrainian contractors, using equipment made in Ukraine and abroad.
Gallery