Burshtyn CHP power unit No. 7

Client:
OJSC Zakhidenergo
Subject:
Reconstruction and technical re-equipment of power unit No. 7 (ALSTOM-POWER, LPC, ACS, turbo generator oil system)
Branch:
Heat power industry
Location:
Ukraine
Terms:
2011

ABOUT PROJECT

Burshtyn CHP power unit No. 7

At the commission of "Zakhidenergo" OJSC, SOYUZ Corporation has performed, together with "ALSTOM-POWER" LPC, the first in Ukraine pilot project: "Reconstruction and technical re-equipment of power unit No. 7 of Burshtyn CHP", including:

  • reconstruction of turbogenerator low-pressure cylinder;

  • reconstruction of the turbine hydraulic control;

  • reconstruction of turbogenerator oil system.

As a result of works, in particular due to the reconstruction of the turbine low-pressure cylinder (LPC), there were achieved the following turbogenerator performance:

  • electrical capacity gain of 12.5 MW as compared to rated capacity (200 MW);

  • efficiency ratio of turbine LPC wheelspace is 89%;

  • decrease of the turbine specific heat (gross) up to 120 kcal/kW/h compared to the results of tests conducted before commence of the turbine LPC reconstruction.