In June 2021, Corporation “SOYUZ” concluded the contract with PJSC “NPC “UKRENERGO” for the reconstruction of SS 750 kV «Vіnnytska» situated on the territory of Комаriv village council, Vinnyytsia rayon, Vinnytsia region.
SS 750/330/110/10 kV «Vinnytska» is the most powerful substation of the South-Western Grid of “UKRENERGO”. Its capacity is 1 124 МVА.
Following the contract Corporation “SOYUZ” is obliged to perform the work under the Employer’s order - reconstruction of SS 750 kV «Vіnnytska» with the replacement of АТ-2, ТPR (phase-shifting transformer) АТ-2, installation of АТ-1, ТPR (phase-shifting transformer) АТ-1 and implementation of progressive technological solutions with passing the work’s results to the employer.
Performing the construction, installation and commissioning is executed by the Ukrainian construction companies. Both the equipment made in Ukraine and abroad is used. Upon the completion of the reconstruction, the capacity and throughput of the substation will increase 2 times, and a further possibility to change the obsolete transformer will appear. Launching of the new modern equipment will provide increasing the reliability of power supply to the consumers of Vinnytsia region.
All the work at SS 750 kV «Vinnytska» is carried out at the operated substationї.
The term of finishing the work is the year 2022.